Two order quantities can produce different unit-cost estimates even when the part drawing stays the same. Fixed effort is spread differently, while material, processing and acceptance assumptions may also change. A useful should-cost discussion makes those assumptions visible before deciding that a supplier quote is too high.
What should-cost is useful for
Use should-cost thinking to identify the material, process, setup, tooling, inspection, yield, and delivery assumptions behind a custom-part quote. Build a transparent model, compare equivalent scope, and ask suppliers to explain material differences. Treat the estimate as a decision aid that improves questions, not as proof of confidential costs or a guaranteed target price.
Begin by defining the deliverable. A machined blank, a finished inspected component and a packaged assembly are different purchasing scopes. The model should represent the accepted item that the business actually needs.
The GAO cost-estimating guide overview emphasizes a technical baseline, assumptions, data, sensitivity analysis and updates. Those disciplines are useful for a custom-part model without copying the documentation scale of a major public program.
Separate known inputs from assumptions and unresolved questions. Record the drawing revision, material, quantity, process route, required quality evidence and delivery basis. An estimate built for an earlier revision should not be used as if it describes the current order.
Drivers you can see on a drawing
Look for material form and removal, deep pockets, slender features, internal corners, multiple access directions and specialized finishes. These features can change the proposed route, but the drawing alone does not reveal the supplier’s actual setup or operating cost.
Review the inspection burden too. A critical hidden feature may need different equipment or additional access. Traceability, special tests, reporting and packaging can be part of the purchased work. Include them in the model if the order requires them.
ASME Y14.5’s public overview concerns communicating dimensional requirements. Clear drawing requirements improve the cost discussion because supplier proposals can address the same geometry and acceptance basis. A general precision note can otherwise hide different interpretations.
Ask which features drive extra setups, tools or verification. Use the answer to identify a design review, not to demand that the supplier remove required operations without a supported alternative.

Table: question list for suppliers
| Cost area | Useful supplier question | Comparison boundary |
|---|---|---|
| Material | Which stock, grade and condition are included? | Same material evidence and delivered state |
| Setup | Which effort is shared across the lot? | Same quantity and repeat-order assumptions |
| Processing | Which features require additional operations? | Same approved geometry and finish |
| Acceptance | What inspection and test scope is included? | Same accepted output and reports |
| Tooling | What is purchased and what changes on revision? | Same ownership, maintenance and change scope |
| Delivery | What packaging and shipment scope is covered? | Same commercial delivery basis |
Ask for explanations at a practical level. A route clarification or separate tooling line can resolve a discrepancy without requiring disclosure of proprietary machine rates.
Where estimates go wrong
A simple model helps reveal the effect of order quantity. Let F be the included fixed lot effort expressed as cost, v the modeled variable cost per accepted part and N the accepted quantity. Then total modeled cost T = F + Nv, and average cost C = F/N + v.
If N doubles while F and v truly remain unchanged, the fixed contribution per part changes from F/N to F/(2N), which is half as large. The variable contribution does not halve. Therefore the total unit estimate does not automatically fall by half.
This is an algebraic illustration without invented prices, shop rates or supplier data. It excludes capacity steps, new tooling, yield changes, order-release costs and other nonlinear effects. If v is estimated per attempted part rather than per accepted part, the yield basis must be handled explicitly and consistently.
NASA’s technical-planning guidance connects technical content, schedule and budget. Use that relationship as a reminder to revisit the estimate after a route or schedule change, not as a mandatory procedure for a commercial custom-part order.
Historical quotes also need context. A different material, inspection package, quantity or delivery condition can invalidate a direct comparison even when the part names are similar.
Pairing with DFM
Connect the model to specific design questions. Could a larger internal radius simplify access? Can a nonfunctional surface have a less demanding requirement? Could an assembly change remove a separate operation? Obtain a technically supported proposal for each candidate.
Keep the original and revised acceptance basis visible. A lower quote obtained by removing a required test or changing material without review is a scope change, not demonstrated efficiency.
NIST’s traceability guidance explains the evidence behind a traceable measurement result. When discussing inspection cost, clarify the actual result and records required instead of treating a broad calibration claim as a complete inspection package.
Approve the revised design and relevant verification before using the proposed savings in a purchasing decision. Update the model with the actual supported route and the quote’s exclusions.

FAQ
These questions address specification details that should be settled before sample approval.
Does a should-cost estimate reveal the supplier’s actual cost?
No. It is a model based on stated assumptions and available evidence. Use it to ask questions and compare scope rather than present it as an audited supplier ledger.
Can a lower estimated unit cost settle the sourcing decision?
No. Review tooling, accepted yield, inspection, delivery scope, revisions and risk alongside the quoted price.
Should every supplier disclose confidential process rates?
No. Request information needed to clarify scope and assumptions, respect confidentiality, and use a level of detail appropriate to the commercial discussion.
Can a DFM change be accepted solely for savings?
No. Engineering must approve the revised requirement and relevant validation before the new cost basis becomes binding.
Ethics of should-cost
Use should-cost to improve an informed negotiation. Do not present guessed rates as audited facts, claim access to another supplier’s confidential data, or describe a model output as the only legitimate selling price.
FAR 15.404-1 distinguishes price analysis from examination of separate cost elements within U.S. federal procurement. That distinction is useful background here; its government contracting procedures are not being imposed on an ordinary commercial RFQ.
Give suppliers an opportunity to identify incorrect assumptions. Compare proposals fairly and preserve the agreed scope. When the model and market responses disagree, investigate the technical and commercial basis before turning the disagreement into an accusation.
CTA
Discuss CNC machining, low-volume manufacturing or injection molding against the actual quantity and revision pattern. Ask which assumptions materially change the proposed route.
Send the controlled files, quantities and acceptance requirements for a comparable quote. Include your open design questions and request clear scope, exceptions and change assumptions.